Construction continues for improvements to Chandler Heights Road from McQueen Road to Gilbert Road (Project: ST1614.401 CHN0240D T009901C). Provided below is information on the upcoming construction schedule, but please remember schedules can be impacted by a variety of factors to include weather, materials scheduling, availability of resources, and coordination with others.
Current Construction Information:
· Landscape crews continue work installing irrigation pipeline on the north side of Chandler Heights from Cooper Rd to 130th St.
· Scheduled to begin Dec. 11, crews will plant trees and shrubs throughout the project area.
· Work is currently taking place to install a concrete valley gutter on the south side of Chandler Heights at 126th St, with 126th St currently closed through Dec. 8. Detour signage is in place to direct travelers around the closure.
· Electric crews are currently working on the northwest corner of Adams Ave and Chandler Heights to install electric conduit for the traffic signal at this location. A temporary traffic signal is in place in the interim and Adams Ave traffic is shifted away from the work activity.
· Scheduled for the week of Dec. 18, paving crews will pave the base course (bottom layer) of asphalt on the south side of Chandler Heights, from Cooper Rd to Adams Ave, and from 124th to 122nd St. Crews will also work to prepare and pave the connection to 132nd St during this pave date as well.
· Scheduled for late December or early January, Adams Ave will be closed on the north side of Chandler Heights for crews to reconstruct the concrete valley gutter at that location.
· Chandler Heights Road remains open for travel during this work with traffic shifted away from the work activity permitting at least one lane of travel in each direction.
· Access to residences and businesses is being maintained.
Thank you for your patience during this work.
Project Info: 480.898.4060 | www.ChandlerAz.gov/ChandlerHeightsMcQueen
|